This is not a bug, but the demo data should be improved, for example lead time for products = 5 days, and security days = 1.
And for the all product the delivery lead time should be grater then the supplier lead time for example in pc1 there is a delivery lead time is 2 days this should be increased to 7 or more.
For some product there is a supplier lead time is very large and delivery lead time is too big that's why on some product the reception is goes in past.
Hello,
This is not a bug, but the demo data should be improved, for example lead time for products = 5 days, and security days = 1.
And for the all product the delivery lead time should be grater then the supplier lead time for example in pc1 there is a delivery lead time is 2 days this should be increased to 7 or more.
For some product there is a supplier lead time is very large and delivery lead time is too big that's why on some product the reception is goes in past.
https:/ /bugs.launchpad .net/openobject -addons/ +bug/770392 this is also like the same but we can't duplicate it .
Because this bug is for reception (Incoming shipment) and the other one is for delivery order.