in some scenario reception is set in the past

Bug #780337 reported by Mihai Satmarean
8
This bug affects 1 person
Affects Status Importance Assigned to Milestone
Odoo Addons (MOVED TO GITHUB)
Fix Released
Low
OpenERP R&D Addons Team 2

Bug Description

I create a sales order with date today, expected date today (my mistake)
I confirm it
System generates a PO, and a reception for that. (perhaps the lead times influence this)

The PO is set for today, and the reception is set for two days in the past.

Is this correct behavior, can this be avoided with restrains?

I know that you guys have a lot of work, I am trying to make my contribution to have a better and more usable product.
Thanks.

Related branches

Revision history for this message
Amit Parik (amit-parik) wrote :

Hello Mihai,

I have checked your issue But I am not able to find the expected date field in either sale order or sale.order.line.

So where you configure the expected date in SO?

Would you please provide the proper steps or screen-shots on this.

Thanks and waiting for your reply!

Changed in openobject-addons:
status: New → Incomplete
Revision history for this message
Mihai Satmarean (mihai-satmarean) wrote :

Hello,
Sorry for misleading you,
The field we are talking about is date_order.

Steps:
- Create a new SO
- Fill everything and Date Order keep it today.
- Confirm the sale order

The system generates a PO
- Go and accept the purchase
-> the purchase will create a reception with the date expected (there are many date fields there, i want to talk about the one that the system thinks that the goods will arrive in my warehouse) two days in the past.

I hope this helos,
If not, I'll make screenshots.

Thanks.
Mihai

Revision history for this message
Amit Parik (amit-parik) wrote :

Hello,

This is not a bug, but the demo data should be improved, for example lead time for products = 5 days, and security days = 1.

And for the all product the delivery lead time should be grater then the supplier lead time for example in pc1 there is a delivery lead time is 2 days this should be increased to 7 or more.

For some product there is a supplier lead time is very large and delivery lead time is too big that's why on some product the reception is goes in past.

https://bugs.launchpad.net/openobject-addons/+bug/770392 this is also like the same but we can't duplicate it .
Because this bug is for reception (Incoming shipment) and the other one is for delivery order.

Thanks.

Changed in openobject-addons:
assignee: nobody → OpenERP R&D Addons Team 2 (openerp-dev-addons2)
importance: Undecided → Low
status: Incomplete → Confirmed
Revision history for this message
Rohan Nayani(Open ERP) (ron-tinyerp) wrote :

Hello,

It has been fixed in lp:~openerp-dev/openobject-addons/trunk-bug-770392-ron with fixed of https://bugs.launchpad.net/openobject-addons/+bug/770392 ,
Revision ID: <email address hidden>
Revision num:4679.

Thanks

Changed in openobject-addons:
status: Confirmed → Fix Committed
Changed in openobject-addons:
status: Fix Committed → Fix Released
To post a comment you must log in.
This report contains Public information  
Everyone can see this information.

Other bug subscribers

Remote bug watches

Bug watches keep track of this bug in other bug trackers.