os33 (olivier-sommier) wrote : Re: Work done on draft task

Hello,

I think that is a bad idea because some computation may be wrong:
I tried with profile service_EN http://demo.openerp.com:8080/ in a project called Bad time computation.
I created a new task and kept it in 'Draft' status with 10 hours in planned hours.
I enter 7 hours in the work done (time spend field).
I saved the task. It seems OK.
But when you come back on this task :
  Planned Hours: 10:00
 Remaining Hours: 10:00 ==>FALSE(?)
 Delay Hours: 07:00 ==>FALSE
 Hours Spent: 07:00

Thanks to fix it !!