I think may be you have misunderstand something, If your 'Time Spent" (working hours) is greater then the planned hours then Remaining Hours will be always in negative because
Planned Hours = Time Spent + Remaining Time
Form your scenario you have planned 8 hours than you have worked 14 hours so Remaining Hours will become -6 and which is correct.
Time Spent (14) + time remaining (-6) = (8)Planned Hours.
So Currently I am closing this issue.
Hope this will help for you.
Hello Dr Ferdinand,
I have checked your issue but it is not a bug.
I think may be you have misunderstand something, If your 'Time Spent" (working hours) is greater then the planned hours then Remaining Hours will be always in negative because
Planned Hours = Time Spent + Remaining Time
Form your scenario you have planned 8 hours than you have worked 14 hours so Remaining Hours will become -6 and which is correct.
Time Spent (14) + time remaining (-6) = (8)Planned Hours.
So Currently I am closing this issue.
Hope this will help for you.
Correct me if I am wrong.
Thanks.