Comment 2 for bug 716882

Revision history for this message
os_33 (olivier-s) wrote :

Hello,

Tested on Version 6.1 RC1.

Create a new project.

Create a first task linked with this project :
 - planned hours = 10
 - add a task work for 3 hours
 - save the task -> Total hours = 10 , Remainning hours =7 OK

Create a second task linked with the previous project
 - planned hours = 0
 - add a task work for 3 hours
 - save the task -> Total hours = 0 , Remainning hours =-3
This second task is used to historize the customers extra requests appeared during the project and not planned at the beginning. I wonder if there is another way to manage this

Go to Reporting>Tasks>Tasks analysis
-total and planned hours =10
-Effective hours = 6
-Remainning hours = 4 !!!!!! instead of 7