Comment 5 for bug 436449

Revision history for this message
Ana Juaristi Olalde (ajuaristio) wrote :

Hi:

+1 to tempo's post.

Security days can cause the packing planned date on past wich is absolutly wrong. Try to fix delivery date for customer 3 days, so you will obtain planned packing date for 2 days before today.
I think something similar to this bug has been discused in another post or bug but I could not find it.

I think planned data functionality should be heavilly reviewed for 6.0 if it's not possible for 5.0. I mean... In so many cases it's no sense fixing delivery for 7 days or 2 days... system should be able to calculate correct delivery data depending on availability of stock and supplier planned delivery data.

This is... if your procurement for product is against stock and you have got stock available for product your delivery time probably will be inmediate. If you haven't got stock, planned data should be calculated depending on your supplier's delivery time or your production delay time. In most of companies it's nosense fixing this delivery or delay datas. Actually, packing planned data has to be fixed by hand.

IMHO ... should we open a new blueprint with correct requierements for this functionality?