project task - bizarre calculation of total hours
Bug #838249 reported by
Ferdinand
This bug report was converted into a question: question #169880: project task - bizarre calculation of total hours.
This bug affects 2 people
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Odoo Addons (MOVED TO GITHUB) |
Opinion
|
Undecided
|
Unassigned |
Bug Description
total hours computation
IMHO remaining hours should only be added if these are positive.
and yes - the planned hours should be reevaluated to avoid negative remaining hours.
To post a comment you must log in.
Hello Dr Ferdinand,
I have checked your issue but it is not a bug.
I think may be you have misunderstand something, If your 'Time Spent" (working hours) is greater then the planned hours then Remaining Hours will be always in negative because
Planned Hours = Time Spent + Remaining Time
Form your scenario you have planned 8 hours than you have worked 14 hours so Remaining Hours will become -6 and which is correct.
Time Spent (14) + time remaining (-6) = (8)Planned Hours.
So Currently I am closing this issue.
Hope this will help for you.
Correct me if I am wrong.
Thanks.