Changelog
task (2.1.2-0ubuntu1~ubuntu12.04.1) precise-backports; urgency=low
* No-change backport to precise (LP: #1130970)
task (2.1.2-0ubuntu1) raring; urgency=low
* New stable upstream release
task (2.1.1-0ubuntu2) quantal; urgency=low
* debian/patches/100_only_stack_size_1.patch: Cherrypick patch from
upstream bug 1048 to fix segfault when running 'task - modify'
(LP: #1032861)
task (2.1.1-0ubuntu1) quantal; urgency=low
* New upstream release
- User Defined Attributes
- Support for 'scheduled' dates for tasks
- New 'ready' report for tasks scheduled for work
- Task expiration via an 'until' date
* Drop all patches: Already included upstream
* debian/rules: task_completion.sh is now named task.sh
task (2.0.0.release-0ubuntu4) quantal; urgency=low
* Add 103_total_active_time.patch: Don't continue accumulating total
active time after an active task is completed.
(LP: #992854)
* Add 104_project_complete_verbosity.patch and 105_affected_verbosity.patch:
Be quieter with feedback if rc.vebose=nothing is specified.
(LP: #992876)
* Add 106_chdir_back_after_edit.patch: Fix segfault in
Context::dispatch() when running task shell. This is because the edit
command was not restoring the current directory.
(LP: #980093)
task (2.0.0.release-0ubuntu3) quantal; urgency=low
* Add 100_fix_uuid_confusion.patch: Fix issue where deleting certain
UUIDs results in deletion of all tasks.
(LP: #992852)
* Add 101_typo_edit_command.patch: Fix invalid command syntax in
task edit command.
(LP: #992866)
* Add 102_fix_incorrect_projects_headers.patch: Fix inverted priority
labels in task projects report.
(LP: #992868)
-- Felix Geyer <email address hidden> Wed, 01 May 2013 17:46:53 +0200