Dependency lag days does not respect the calendar

Bug #1081499 reported by Beltrachi
6
This bug affects 1 person
Affects Status Importance Assigned to Milestone
planner
New
Medium
planner (Ubuntu)
New
Undecided
Unassigned

Bug Description

The dependency lag should take into account the default calendar and do not count the weekend days as lag days.

Easier to see in an example:
You have 2 tasks of 1d work and mark a dependency from A to B with a lag of 3 days.

A -> B (3 days)

The wrong plannig says:
Planning (Project starts on Thursday):
Thu: A
Fri: -
Sat: - (weekend)
Sun: - (weekend)
Mon: B

The plannig should say:
Thu: A
Fri: -
Sat: - (weekend)
Sun: - (weekend)
Mon: -
Tue: -
Wed: B

Extra info:

$ lsb_release -rd
Description: Ubuntu 12.04.1 LTS
Release: 12.04

$ apt-cache policy planner
planner:
  Installed: 0.14.5-1ubuntu3
  Candidate: 0.14.5-1ubuntu3
  Version table:
 *** 0.14.5-1ubuntu3 0
        500 http://archive.ubuntu.com/ubuntu/ precise/universe amd64 Packages
        100 /var/lib/dpkg/status

Revision history for this message
Alexandre Franke (afranke) wrote :

This is not the right place to report this. Please file it at https://bugzilla.gnome.org/enter_bug.cgi?product=planner

Revision history for this message
Beltrachi (beltrachi) wrote :
Changed in planner:
importance: Unknown → Medium
status: Unknown → New
To post a comment you must log in.
This report contains Public information  
Everyone can see this information.

Other bug subscribers

Remote bug watches

Bug watches keep track of this bug in other bug trackers.