[Maverick] Calendar ignores preference "Work Days" and "Day begins/ends"

Bug #665397 reported by Oliver Joos
18
This bug affects 3 people
Affects Status Importance Assigned to Milestone
Evolution
New
Medium
evolution (Ubuntu)
Confirmed
Undecided
Unassigned

Bug Description

Binary package hint: evolution

I tested evolution 2.28.3-0 (Ubuntu Lucid), 2.30.3-1 (Ubuntu Maverick) and 2.32.0-2-fc14 (pre-release of fedora 14) - only Maverick is affected.

To reproduce:
1. Start Evolution and open Calendar in Day or Work Week view
2. Open menu Edit - Preferences - Calendar and Tasks - General
3. Alter settings of "Work Days" or "Day begins/ends"
=> No change in Day or Work Week view. Closing preferences window or restarting Evolution does not help. Work Days are always Mon-Fri, and day begins always at 9:00am and ends at 5:00pm.

Revision history for this message
Brian Fuller (slink3r) wrote :

I'm getting the same thing in maverick i386 as well.

Changed in evolution (Ubuntu):
status: New → Incomplete
status: Incomplete → Confirmed
Changed in evolution:
importance: Unknown → Medium
status: Unknown → New
Revision history for this message
Marcel Stimberg (marcelstimberg) wrote :

Thank you for taking the time to report this bug and helping to make Ubuntu better. This particular bug has already been reported and is a duplicate of bug 649543, so it is being marked as such. Please look at the other bug report to see if there is any missing information that you can provide, or to see if there is a workaround for the bug. Additionally, any further discussion regarding the bug should occur in the other report. Please continue to report any other bugs you may find.

To post a comment you must log in.
This report contains Public information  
Everyone can see this information.

Other bug subscribers

Remote bug watches

Bug watches keep track of this bug in other bug trackers.