[6.0.2]Gantt view incorrect displays task end date
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Odoo Web Client |
Won't Fix
|
Low
|
OpenERP R&D Web Team | ||
6.0 |
Won't Fix
|
Undecided
|
Unassigned | ||
Trunk |
Won't Fix
|
Low
|
OpenERP R&D Web Team |
Bug Description
System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term planning installed.
I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.
Task Scheduler now computes OK (https:/
But If I switch to the Gantt view the Task2's end date is not displayed correct.
Task2 starts correct at 26/04/2011 08:00 and should end 29/04/2011 18:00. But it ends 27/04/2011 20:00.
The problem is, that Task2's end date = start date+36hour, but the working time is not taked in consideration.
Thank you.
Arpi
tags: | added: date end time |
Hello,
I have tested this issue with latest trunk and stable and I found that this project task Gantt view working fine with the trunk but problem occurred at the stable-6.0.2. So, I am confirming this issue.
Thanks You.