make_mo date_planned incorrect
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Odoo Addons (MOVED TO GITHUB) |
Confirmed
|
Wishlist
|
OpenERP R&D Addons Team 3 |
Bug Description
OpenERP 6.1
Ubuntu 10.04/10.10
Running scheduler
When OpenERP scheduler runs make_mo it uses the _default value for date_planned.
This ends up as TODAY 00:00:00
This date is affected by produce_delay and manufacturing_lead which I have set to 0 for simplicity
Once this date is settled it comes up as TODAY 10:00am for every MO which is GMT + the current time zone GMT+10
This date_planned should ideally come out at least as 7:00am which is our resource_calendar start time for manufacturing.
In the case of say a time zone GMT-10 then I am assuming that the date_planned will come out as YESTERDAY 14:00 which is not nice.
Maybe the start time/date can be adjusted according to a setting (res_comany.
What is the strategy for planning manufacturing?
As far as I can see there is no real planning involved. It seems take today's date and applies to every MO without regard to workcenter load or duplicate products. Is the planning intended to be manual?
Hello,
As per your suggestion we have to set manufacturing planned_date 's time based on Company's manufacturing start time.
So it's good improvement, that's why I am setting this as a "Wishlist".
Thanks for reporting!