[Trunk/6.1][project_long_term] Create new project based on template: tasks and phases wrongly linked to corresponding projects
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Odoo Addons (MOVED TO GITHUB) |
Won't Fix
|
Medium
|
OpenERP R&D Addons Team 1 |
Bug Description
OpenERP 6.1.1 Addons Revision number: 6682
Linux Lynx 10.04/ Google Chrome 17.0.963.56
I have installed project_long_term and then continued by configurating a project, phases (linked between themselves) and tasks as shown in the video(see below).
Upon creation of project from template, the tasks of the new project were attached to the template phases and the phase of the new project were attached to the template's tasks. I was not expecting this muddled scenario but rather correct links between tasks, phases and their corresponding project.
Sidenote question: Is it common behavior that when converting a project its related tasks disappear? And then they reappear upon creation of a project from the template?
Related branches
- OpenERP Core Team: Pending requested
-
Diff: 79 lines (+62/-0)1 file modifiedproject_long_term/project_long_term.py (+62/-0)
Changed in openobject-addons: | |
assignee: | nobody → OpenERP R&D Addons Team 1 (openerp-dev-addons1) |
importance: | Undecided → Medium |
status: | New → Confirmed |
Changed in openobject-addons: | |
status: | Confirmed → In Progress |
summary: |
- [6.1][project_long_term] Create new project based on template: tasks and - phases wrongly linked to corresponding projects + [Trunk/6.1][project_long_term] Create new project based on template: + tasks and phases wrongly linked to corresponding projects |
Changed in openobject-addons: | |
status: | In Progress → Fix Committed |
Hello,
Thanks For Reporting.
It has been Fixed in https:/ /code.launchpad .net/~openerp- dev/openobject- addons/ trunk-bug- 959219- tpa
revision-id: <email address hidden>
revno: 6776
It will be available in trunk soon.