mrp - moving an MO to another day does not change the workorders date and time
Bug #805503 reported by
Mihai Satmarean
This bug affects 1 person
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Odoo Addons (MOVED TO GITHUB) |
Fix Committed
|
Wishlist
|
OpenERP R&D Addons Team 2 |
Bug Description
I go to a MO and change the date from
01.07.2011 to 20.07.2011
But the workorders still remain in the 01.07.2011.
I understand that moving a workorder does not change the MO date, but I believe that changing MO start date should reschedule all the workorders start date.
Thanks
Related branches
lp:~openerp-dev/openobject-addons/trunk-bug-805503-ksa
Rejected
for merging
into
lp:openobject-addons
- Rucha (Open ERP) (community): Approve
- qdp (OpenERP): Pending requested
-
Diff: 22 lines (+3/-2)1 file modifiedmrp_operations/mrp_operations.py (+3/-2)
Changed in openobject-addons: | |
status: | Confirmed → In Progress |
Changed in openobject-addons: | |
importance: | Low → Wishlist |
To post a comment you must log in.
Hello,
I have checked this bug report and I am agree with this.
The problem is when we create a MO and confirm it then the work order will be generated and the MO 's scheduled date passed in to work order's scheduled date.
But after the confirmation of the production order we are able to change the scheduled date and If we change the scheduled date that does not reflect in to workorder.
So I would like to suggest if the MO is confirmed the the scheduled date becomes a read-only and it will not allow to change other wise when we change the scheduled date of MO it will reflect on work-order as well as.
Thanks.