Comment 5 for bug 427733

Revision history for this message
Raphaƫl Valyi - http://www.akretion.com (rvalyi) wrote : Re: [Bug 427733] Re: error with planed date on purchase order for product MTS

Just a remark: do you think we can change the meaning of that field in
version 5.0 with the risk to impact everyone or every module using that
field?
May be it should be changed on trunk only, no?

On Wed, Mar 31, 2010 at 2:33 PM, Stephane (Open ERP) <email address hidden>wrote:

> ** Changed in: openobject-addons
> Milestone: 5.0.8 => 5.0.9
>
> --
> error with planed date on purchase order for product MTS
> https://bugs.launchpad.net/bugs/427733
> You received this bug notification because you are subscribed to
> OpenObject Addons.
>
> Status in OpenObject Addons Modules: Confirmed
>
> Bug description:
> Hi,
>
> There is a problem with generated planed date on purchase order when a
> manufacturing order want a product "make to stock" with 0 in stock.
>
> (0 security days for this exemple)
>
> When I sale today (september 11) a velo with delivery in 30 days to
> customer (oktober 11), 3 days for manufacturing and I have 0 handelbars
> (MTS) in stock, this handelbar have 5 days from supplier to me, OpenERP
> should generate a purchase order for this handelbar for planed date 30-3
> days = in 27 days (oktober 8), but the system generates a planed date for
> today-5 days = there 5 days (september 6) -> in the past !!!
>
> It unusable for calculating supply in a production !!
>
> - version 5.0.3 with JIT module -
>
>
>