openerp v7 project module: resource leaves ignored
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Odoo Addons (MOVED TO GITHUB) |
New
|
Undecided
|
Unassigned |
Bug Description
Hi guys.
I am trying to get Resource leaves calculated correctly with the Phase Scheduler. As there is NO propper documentation for project long term in v7 I am having a hard time finding out if i am just doing something wrong or if the Scheduler is just broken. I have tried every configuration possible in the last few days. Always downloding the latest nightly DEB available.
Please test if my assumption that this is a bug is correct.
This is what i tried.
Create Working time.
Create employee with Working time
Create project.
Assign employee to Team.
Set default Working time to project.
Create Phase.
Assign employee to Team.
Create task.
Assign task to employee.
Set a long estimated duration of hours spanning several days.
Run the Phase Scheduler.
Phase lasts X days.
Create a Ressource leave for the employee using the full worktime lasting half of the just calculated Phase.
Run the Scheduler again.
Phase is still the same X days.
Expected result would be a longer phase as the Ressource is absent.
Nightly used 05.12.2013.
RELATED TO:
https:/
Has been reported over a year and placed on "Wishlist"(?).
How is this a candidate for Wishlist if there is even a Menue to enter leaves?
From looking at the code of the scheduler there seems to be no indication that resource attendency is queried at any point.
Suggesting removing this "decorative" menue as long as the scheduler is not functional.
description: | updated |
Does anyone plan to invesitage this one?
The issue criples the project module and takes any significance from the "TeamPlanning" function.