Preselect the date of 'due for' if 'starting on' is filled

Bug #797359 reported by François Boulogne
14
This bug affects 3 people
Affects Status Importance Assigned to Milestone
GTG
Fix Released
Wishlist
Izidor Matušov

Bug Description

Hi,

Current behaviour:
1/ I choose a date for which my task starts (eg 1/1/2018)
2/ I choose a date for which my task should end (eg 1/1/2020)

The problem is that the second calendar (due for) is displayed with the current date. I wish that the second calendar knows that the task starts on 1/1/2018 and preselects this day because the task could not be done before ;)

Many thanks.

Revision history for this message
Lionel Dricot (ploum-deactivatedaccount) wrote :

Really cool idea, will try to do that for 0.3 release

Changed in gtg:
status: New → Confirmed
importance: Undecided → Wishlist
milestone: none → 0.3
Revision history for this message
François Boulogne (sciunto.org) wrote :

AFAIK, the problem is solved in the trunk version...

Revision history for this message
Izidor Matušov (izidor) wrote :

Yes, it seems that I've fixed it when solving calendar problems few weeks ago.

Changed in gtg:
status: Confirmed → Fix Committed
assignee: nobody → Izidor Matušov (izidor)
milestone: 0.3 → 0.2.9
Izidor Matušov (izidor)
Changed in gtg:
status: Fix Committed → Fix Released
Revision history for this message
François Boulogne (sciunto.org) wrote :

I reopen this bug because the version coming from the bzr (trunk) repository seems to do not behave as expected.

Revision history for this message
Izidor Matušov (izidor) wrote :

Thank you for catching that regression! I opened the bug #1036955 for it.

To post a comment you must log in.
This report contains Public information  
Everyone can see this information.

Other bug subscribers

Remote bug watches

Bug watches keep track of this bug in other bug trackers.