Closed Dates Editor Displaying Incorrect Closed Duration
Bug #1594937 reported by
Jennifer Pringle
This bug affects 4 people
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
Evergreen |
Fix Released
|
Undecided
|
Unassigned | ||
2.10 |
Fix Released
|
Undecided
|
Unassigned | ||
2.11 |
Fix Released
|
Undecided
|
Unassigned |
Bug Description
Evergreen 2.10
(Admin -> Local Administration -> Closed Dates Editor)
Closures are displaying with an extra closed day in the staff client in 2.10. For example, when I enter July 1st as a closed date it displays as "From 2016-07-01 at 00:00 through 2016-07-02 at 23:59". It should display as "From 2016-07-01 at 00:00 through 2016-07-01 at 23:59"
The closed date is correct in the database.
This issue is present for all types of closures - single day, multiple date, and detailed.
I have tested this on our 2.10 servers as well as Equinox's 2.10 community server.
I have also tested and confirmed that this issue is not present in 2.8 or 2.9.
Changed in evergreen: | |
milestone: | none → 2.next |
Changed in evergreen: | |
status: | Fix Committed → Fix Released |
Changed in evergreen: | |
milestone: | 2.next → 2.12-beta |
To post a comment you must log in.
I just confirmed it on a system running master. It does not affect our production system running 2.9.