action from the user should go in the priority queue
Bug #833725 reported by
Lionel Dricot
This bug affects 1 person
Affects | Status | Importance | Assigned to | Milestone | |
---|---|---|---|---|---|
GTG |
Fix Released
|
Medium
|
Unassigned |
Bug Description
1) launch gtg with *a lot* of closed tasks
2) While it is still loading, mark one task as Done
3) observe that your change is not processed until all the closed tasks have been processed.
This is because the "mark as done" is sent in the normal queue while it should go in the priority queue
Changed in gtg: | |
status: | New → Confirmed |
importance: | Undecided → Medium |
milestone: | none → 0.2.9 |
Changed in gtg: | |
assignee: | nobody → Lionel Dricot (ploum) |
status: | Confirmed → In Progress |
Changed in gtg: | |
status: | Fix Committed → In Progress |
Changed in gtg: | |
status: | Fix Committed → Fix Released |
To post a comment you must log in.
fixed with rev 1033