mrp - moving an MO to another day does not change the workorders date and time

Bug #805503 reported by Mihai Satmarean
8
This bug affects 1 person
Affects Status Importance Assigned to Milestone
Odoo Addons (MOVED TO GITHUB)
Fix Committed
Wishlist
OpenERP R&D Addons Team 2

Bug Description

I go to a MO and change the date from

01.07.2011 to 20.07.2011

But the workorders still remain in the 01.07.2011.

I understand that moving a workorder does not change the MO date, but I believe that changing MO start date should reschedule all the workorders start date.

Thanks

Related branches

Revision history for this message
Amit Parik (amit-parik) wrote :

Hello,

I have checked this bug report and I am agree with this.

The problem is when we create a MO and confirm it then the work order will be generated and the MO 's scheduled date passed in to work order's scheduled date.

But after the confirmation of the production order we are able to change the scheduled date and If we change the scheduled date that does not reflect in to workorder.

So I would like to suggest if the MO is confirmed the the scheduled date becomes a read-only and it will not allow to change other wise when we change the scheduled date of MO it will reflect on work-order as well as.

Thanks.

Changed in openobject-addons:
assignee: nobody → OpenERP R&D Addons Team 2 (openerp-dev-addons2)
importance: Undecided → Low
status: New → Confirmed
Revision history for this message
Mihai Satmarean (mihai-satmarean) wrote :

Hi,

I was hoping that you will find a way to leave it writable, but fix the re-scheduling of the work orders,
it would be very hard for us to not be able to do that.

As a workaround, after you change the order's date, we press the "Change QTY" button and the workorders get re-scheduled.

We have a flexible production mode, and also lots of thing can go bad, we make a lot of testing on the products, so it happens often that not all the work scheduled for a day is finished, so we need to re-schedule often.

Please do not make it read only, but find a more elegant way of rescheduling.

Thanks!

Changed in openobject-addons:
status: Confirmed → In Progress
Revision history for this message
Kirti Savalia(OpenERP) (ksa-openerp) wrote :

Hello,
 Thanks For Reporting.
 It has been Fixed in lp:~openerp-dev/openobject-addons/trunk-bug-805503-ksa
 Revision No : 4898
 Revision ID : <email address hidden>

Thanks.

Changed in openobject-addons:
status: In Progress → Fix Committed
Changed in openobject-addons:
importance: Low → Wishlist
Revision history for this message
Mihai Satmarean (mihai-satmarean) wrote :

The fix works for me. No side effects till now.

To post a comment you must log in.
This report contains Public information  
Everyone can see this information.

Other bug subscribers

Remote bug watches

Bug watches keep track of this bug in other bug trackers.