I've 3 tasks : one with 23 days left, the other with 10 days left and the last one with 8 days left.
For whatever reason, the 23 days left is always between 8 and 10. I suspect it's a string alphabetical sort (and that's why tasks with no days left are just next the one with only 1 day left)
Changed in gtg: | |
assignee: | nobody → bertrand-rousseau |
milestone: | none → 0.1rc |
status: | New → Fix Released |
To post a comment you must log in.
I'm running version 0.2.4 and the date sorting is still complete screwed up. It seems to sort the dates according to the way the appear ("Today", "Tomorrow", "5 days ago", "In 15 days") instead of by the numerical date (by year, month and then day) as it should. Makes the program almost unusable!